Sierra Leone
Newton & Lungi
Environmental
Community Health and Safety Officer (Site supervision)
EDSA (World Bank)
- In Progress
1St January, 2025
In Progress
$75 Million (USD)
Have a project in mind?
Regional Emergency Solar Power Intervention Project (RESPITE)
The teams are currently installing the PV panels on site, and the poles and cables installation will commence soon. Compensation payments to PAPs have been made for Lungi and partially Newton (Newton – Benguema).
However, for (Benguema – Tombo), EDSA will inform us when the process will commence.
The project comprises an on-grid PV plant of 30 MWac (with at least 37.5 MWp) and a Battery Energy Storage System (BESS) of at least 15 MW/15 MWh at the Newton site and an on-grid PV plant of at least 10 MWac (12.5 MWp) with a new Battery Energy Storage System (BESS) of at least 6 MW/6 MWh at the Lungi site; and a two-year Operations and Maintenance (O&M) contract.
Project in progress. The project commenced on 1st January 2025; however, site visits began on 1st June 2025.